Ongoing 45-month delay UPRERAPRJ7313

Boulevard Walk (Phase 3)

by Regal Emporia Infratech Private Limited · Gautam Buddha Nagar

Completion on record
31 Oct 2025
Declared 31 Jan 2022 · slipped 45 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ7313
Gautam Buddha Nagar
Registered
10 Aug 2017
Type: Ongoing
Proposed period
87 mo
Declared completion
31 Jan 2022
original commitment
Latest on record
31 Oct 2025
after 3 extensions
Documents on portal
15
filed with UP-RERA
01

Registration details

Project name
Boulevard Walk (Phase 3)
RERA registration no.
UPRERAPRJ7313
Registration type
Ongoing
Registration date
10 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+45months later than promised

Declared completion moved from 31 Jan 2022 to 31 Oct 2025 over 3 registered extensions.

#FromToΔReason on record
131 Jan 202230 Jul 2022+6moSix months extension in view of force...
230 Jul 202229 Sep 2023+14mo
329 Sep 202331 Oct 2025+25mo
Net slip vs first declared date+45moto 31 Oct 2025

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Regal Emporia Infratech Private Limited
Type
Company
Registered office
GROUND FLOOR, TOWER B, TAPASYA CORP. HEIGHTS, SECTOR 126, NOIDA, (U.P.)
Projects on the register
4
Complaints · promoter-wide
138138 (Under Registration - 3 )
Complaints · this project
17filed against Boulevard Walk (Phase 3)

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Boulevard Walk (Phase 3) RERA registered?

Yes. Boulevard Walk (Phase 3) is registered with UP-RERA under registration number UPRERAPRJ7313, registered on 10 Aug 2017.

Is Boulevard Walk (Phase 3) delayed?

Yes. It was declared for completion by 31 Jan 2022, but the date on record is now 31 Oct 2025, a slip of about 45 months across 3 registered extensions.

Who is the developer of Boulevard Walk (Phase 3)?

Regal Emporia Infratech Private Limited, which has 4 project(s) registered with UP-RERA and 138 complaint(s) on record across its projects.

How many complaints are filed against Boulevard Walk (Phase 3)?

17 complaint(s) are recorded against Boulevard Walk (Phase 3) specifically on the UP-RERA portal.

Where can I verify Boulevard Walk (Phase 3)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ7313. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Boulevard Walk (Phase 3). Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation