Ongoing 89-month delay UPRERAPRJ3122

Kvd Windpark

by Kv Developers Private Limited · Gautam Buddha Nagar

Completion on record
10 Mar 2029
Declared 07 Oct 2021 · slipped 89 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ3122
Gautam Buddha Nagar
Registered
28 Jul 2017
Type: Ongoing
Proposed period
Declared completion
07 Oct 2021
original commitment
Latest on record
10 Mar 2029
after 2 extensions
Documents on portal
17
filed with UP-RERA
01

Registration details

Project name
Kvd Windpark
RERA registration no.
UPRERAPRJ3122
Registration type
Ongoing
Registration date
28 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+89months later than promised

Declared completion moved from 07 Oct 2021 to 10 Mar 2029 over 2 registered extensions.

#FromToΔReason on record
107 Oct 202106 Apr 2022+6moSix months extension in view of force...
206 Apr 202210 Mar 2029+83mo
Net slip vs first declared date+89moto 10 Mar 2029

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Kv Developers Private Limited
Type
Company
Registered office
A-19, Ground Floor, Noida-201301
Projects on the register
1
Complaints · promoter-wide
105105 (Under Registration - 0 )
Complaints · this project
98filed against Kvd Windpark

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Kvd Windpark RERA registered?

Yes. Kvd Windpark is registered with UP-RERA under registration number UPRERAPRJ3122, registered on 28 Jul 2017.

Is Kvd Windpark delayed?

Yes. It was declared for completion by 07 Oct 2021, but the date on record is now 10 Mar 2029, a slip of about 89 months across 2 registered extensions.

Who is the developer of Kvd Windpark?

Kv Developers Private Limited, which has 1 project(s) registered with UP-RERA and 105 complaint(s) on record across its projects.

How many complaints are filed against Kvd Windpark?

98 complaint(s) are recorded against Kvd Windpark specifically on the UP-RERA portal.

Where can I verify Kvd Windpark's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ3122. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Kvd Windpark. Straight answers, before you sign anything.