Registration details
- Project name
- Sikka Karnam Greens
- RERA registration no.
- UPRERAPRJ5764
- Registration type
- Ongoing
- Registration date
- 04 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 30 Jun 2022 to 31 Oct 2026 over 3 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 30 Jun 2022 | 29 Dec 2022 | +6mo | Six months extension in view of force... |
| 2 | 29 Dec 2022 | 31 Oct 2025 | +34mo | — |
| 3 | 31 Oct 2025 | 31 Oct 2026 | +12mo | — |
| Net slip vs first declared date | +52mo | to 31 Oct 2026 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Sikka Infrastructure Pvt Ltd
- Type
- Company
- Registered office
- C60 PREET VIHAR DELHI-110092
- Projects on the register
- 1
- Complaints · promoter-wide
- 330330 (Under Registration - 6 )
- Complaints · this project
- 297filed against Sikka Karnam Greens
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
15 documents filed on the UP-RERA portal for UPRERAPRJ5764. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Sikka Karnam Greens RERA registered?
Yes. Sikka Karnam Greens is registered with UP-RERA under registration number UPRERAPRJ5764, registered on 04 Aug 2017.
Is Sikka Karnam Greens delayed?
Yes. It was declared for completion by 30 Jun 2022, but the date on record is now 31 Oct 2026, a slip of about 52 months across 3 registered extensions.
Who is the developer of Sikka Karnam Greens?
Sikka Infrastructure Pvt Ltd, which has 1 project(s) registered with UP-RERA and 330 complaint(s) on record across its projects.
How many complaints are filed against Sikka Karnam Greens?
297 complaint(s) are recorded against Sikka Karnam Greens specifically on the UP-RERA portal.
Where can I verify Sikka Karnam Greens's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ5764. This page mirrors that public record for convenience.