Ongoing 24-month delay UPRERAPRJ6091

Parsvnath Palacia Phase-I

by Parsvnath Developers Limited · Gautam Buddha Nagar

Completion on record
14 Dec 2021
Declared 31 Dec 2019 · slipped 24 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ6091
Gautam Buddha Nagar
Registered
31 Jul 2017
Type: Ongoing
Proposed period
36 mo
Declared completion
31 Dec 2019
original commitment
Latest on record
14 Dec 2021
after 3 extensions
Documents on portal
16
filed with UP-RERA
01

Registration details

Project name
Parsvnath Palacia Phase-I
RERA registration no.
UPRERAPRJ6091
Registration type
Ongoing
Registration date
31 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+24months later than promised

Declared completion moved from 31 Dec 2019 to 14 Dec 2021 over 3 registered extensions.

#FromToΔReason on record
131 Dec 201930 Dec 2020+12mo
230 Dec 202029 Jun 2021+6moSix months extension in view of force...
329 Jun 202114 Dec 2021+6mo
Net slip vs first declared date+24moto 14 Dec 2021

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Parsvnath Developers Limited
Type
Company
Registered office
Parsvnath Tower, Near Shahdara Metro Station Shahdara Delh-110032
Projects on the register
18
Complaints · promoter-wide
414414 (Under Registration - 0 )
Complaints · this project
27filed against Parsvnath Palacia Phase-I

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Parsvnath Palacia Phase-I RERA registered?

Yes. Parsvnath Palacia Phase-I is registered with UP-RERA under registration number UPRERAPRJ6091, registered on 31 Jul 2017.

Is Parsvnath Palacia Phase-I delayed?

Yes. It was declared for completion by 31 Dec 2019, but the date on record is now 14 Dec 2021, a slip of about 24 months across 3 registered extensions.

Who is the developer of Parsvnath Palacia Phase-I?

Parsvnath Developers Limited, which has 18 project(s) registered with UP-RERA and 414 complaint(s) on record across its projects.

How many complaints are filed against Parsvnath Palacia Phase-I?

27 complaint(s) are recorded against Parsvnath Palacia Phase-I specifically on the UP-RERA portal.

Where can I verify Parsvnath Palacia Phase-I's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ6091. This page mirrors that public record for convenience.