Ongoing 63-month delay UPRERAPRJ8592

Panchsheel Greens - Ii (Tower - D1,d2& E5)

by Panchsheel Buildtech Pvt. Ltd. · Select

Completion on record
30 Nov 2026
Declared 31 Aug 2021 · slipped 63 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ8592
Gautam Buddha Nagar
Registered
12 Aug 2017
Type: Ongoing
Proposed period
58 mo
Declared completion
31 Aug 2021
original commitment
Latest on record
30 Nov 2026
after 3 extensions
Documents on portal
17
filed with UP-RERA
01

Registration details

Project name
Panchsheel Greens - Ii (Tower - D1,d2& E5)
RERA registration no.
UPRERAPRJ8592
Registration type
Ongoing
Registration date
12 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarSelect
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+63months later than promised

Declared completion moved from 31 Aug 2021 to 30 Nov 2026 over 3 registered extensions.

#FromToΔReason on record
131 Aug 202128 Feb 2022+6moSix months extension in view of force...
228 Feb 202227 Nov 2023+21mo
327 Nov 202330 Nov 2026+36mo
Net slip vs first declared date+63moto 30 Nov 2026

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Panchsheel Buildtech Pvt. Ltd.
Type
Company
Registered office
H-169 Sector 63 Noida, Gautam Buddha Nagar, U.P.
Projects on the register
18
Complaints · promoter-wide
281281 (Under Registration - 3 )
Complaints · this project
11filed against Panchsheel Greens -...

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Panchsheel Greens - Ii (Tower - D1,D2& E5) RERA registered?

Yes. Panchsheel Greens - Ii (Tower - D1,D2& E5) is registered with UP-RERA under registration number UPRERAPRJ8592, registered on 12 Aug 2017.

Is Panchsheel Greens - Ii (Tower - D1,D2& E5) delayed?

Yes. It was declared for completion by 31 Aug 2021, but the date on record is now 30 Nov 2026, a slip of about 63 months across 3 registered extensions.

Who is the developer of Panchsheel Greens - Ii (Tower - D1,D2& E5)?

Panchsheel Buildtech Pvt. Ltd., which has 18 project(s) registered with UP-RERA and 281 complaint(s) on record across its projects.

How many complaints are filed against Panchsheel Greens - Ii (Tower - D1,D2& E5)?

11 complaint(s) are recorded against Panchsheel Greens - Ii (Tower - D1,D2& E5) specifically on the UP-RERA portal.

Where can I verify Panchsheel Greens - Ii (Tower - D1,D2& E5)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ8592. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Panchsheel Greens - Ii (Tower - D1,d2& E5). Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation