Registration details
- Project name
- Mirage Phase Ii
- RERA registration no.
- UPRERAPRJ4008
- Registration type
- Ongoing
- Registration date
- 29 Jul 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 31 Dec 2024 to 30 Jun 2025 over 1 registered extension.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 31 Dec 2024 | 30 Jun 2025 | +6mo | Six months extension in view of force... |
| Net slip vs first declared date | +6mo | to 30 Jun 2025 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Imperia Structures Ltd
- Type
- Company
- Registered office
- A-25, Mohan Co-operative Industrial Estate Mathura Road, New Delhi-110044
- Projects on the register
- 8
- Complaints · promoter-wide
- 341341 (Under Registration - 3 )
- Complaints · this project
- 22filed against Mirage Phase Ii
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
16 documents filed on the UP-RERA portal for UPRERAPRJ4008. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Mirage Phase Ii RERA registered?
Yes. Mirage Phase Ii is registered with UP-RERA under registration number UPRERAPRJ4008, registered on 29 Jul 2017.
Is Mirage Phase Ii delayed?
Yes. It was declared for completion by 31 Dec 2024, but the date on record is now 30 Jun 2025, a slip of about 6 months across 1 registered extension.
Who is the developer of Mirage Phase Ii?
Imperia Structures Ltd, which has 8 project(s) registered with UP-RERA and 341 complaint(s) on record across its projects.
How many complaints are filed against Mirage Phase Ii?
22 complaint(s) are recorded against Mirage Phase Ii specifically on the UP-RERA portal.
Where can I verify Mirage Phase Ii's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ4008. This page mirrors that public record for convenience.