Migsun Nehru Place 3 is registered with UP-RERA under registration number UPRERAPRJ585500/05/2024, registered on 01 May 2024 by Ansal It City & Parks Limited. The completion date on file is 10 Oct 2028. This page mirrors the project's public UP-RERA record, with 43 filed documents you can open on the official UP-RERA portal.
Registration details
- Project name
- Migsun Nehru Place 3
- RERA registration no.
- UPRERAPRJ585500/05/2024
- Registration type
- New
- Registration date
- 01 May 2024
- Proposed start
- 01 Nov 2023
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- IT SEZ-1A
- Record source
- up-rera.in
Promoter track record
The promoter's wider record on the register, as filed with UP-RERA.
- Promoter
- Ansal It City & Parks Limited
- Type
- Company
- Registered office
- 201, Nirmal Towers Barakhamba Road NA Delhi New Delhi
- Projects on the register
- 4
Every figure above is as filed with UP-RERA; open the promoter's own page for each registration, and verify on up-rera.in before you act.
Verify this record in four steps
- Open up-rera.in and choose the registered projects search.
- Search the registration number exactly as printed here, UPRERAPRJ585500/05/2024, rather than the project name.
- On the record, read the promoter, the project address, the registration date and the declared completion date, and compare them with the documents you were shown.
- Open the filed documents, the sanctioned plan and the affidavits, and confirm the unit you are offered belongs to this registered project and phase.
Documents on record
43 documents filed on the UP-RERA portal for UPRERAPRJ585500/05/2024. Each opens on the official portal record.
Land, build & cost
The UP-RERA register does not publish land area, unit, tower or floor counts, or cost lines — none of those are fields on the project's register entry. The figures below are this tracker's own reading of the certificates filed on the portal: taken off scanned PDFs, and not re-checked line by line against the paper. Treat them as our enrichment, not as the record — open the source document before you act on any of them.
Site coordinates read from the same filings: 28.46356222, 77.53889166 — view on map ↗. A coordinate is not a UP-RERA register field; the register records the district, tehsil and address shown above.
Construction progress
How far the money and the build clock have moved, from the certified figures on the project's filings. View the source certificate (PDF) →
58% of the registered build period has passed; 4% of the estimated cost is certified spent. The spend figure comes from the CA certificate linked above, the clock from the registered start and completion dates on the register.
A snapshot from certified filings, not a live feed; the build clock is computed from the registered start and current completion date. Verify at up-rera.in.
Bank account
The collection account into which buyers deposit, as named on the project's certificate filed with UP-RERA. View the source certificate (PDF) →
Project team
The consultants named on the project's architect and engineer certificates. View the source certificate (PDF) →
- Architect
- KULMEET SHANGARILicence CA/97/21741
- Structural engineer
- Yatendra PaliwalYP & ASSOCIATES
Development & infrastructure
Committed works as stated in the project's development affidavit on the portal. View the source certificate (PDF) →
- Excavation
- 05.12.2023 - 31.05.2024
- Structure
- 01.06.2024 - 31.12.2027
- Facade
- 25.10.2026 - 05.08.2027
- Elevator
- 25.04.2026 - 30.09.2028
- Core Fit Out
- 25.06.2026 - 30.09.2028
- Services
- 25.08.2026 - 30.09.2028
- Earthing & Lightning Protection
- 05.08.2027 - 30.09.2028
- Hvac Low Side
- 05.08.2027 - 30.09.2028
- Hvac High Side
- 05.11.2027 - 30.09.2028
- IBMS
- 02.03.2028 - 30.09.2028
- Electrical Low Side
- 15.08.2027 - 30.09.2028
- Electrical High Side
- 15.10.2027 - 30.09.2028
- Solar
- 25.08.2027 - 30.09.2028
- Security System
- 05.03.2028 - 30.09.2028
- DG
- 05.06.2028 - 30.09.2028
- STP
- 25.09.2027 - 30.09.2028
- WTP
- 28.09.2027 - 30.09.2028
- Plumbing
- 05.03.2026 - 30.09.2028
- Fire fighting
- 10.03.2026 - 30.09.2028
- Signage
- 05.04.2028 - 30.09.2028
- Stacker
- 15.04.2028 - 30.09.2028
- External Development
- 30.05.2027 - 30.09.2028
Other projects nearby
Frequently asked
Is Migsun Nehru Place 3 RERA registered?
Yes. Migsun Nehru Place 3 is registered with UP-RERA under registration number UPRERAPRJ585500/05/2024, registered on 01 May 2024.
When is Migsun Nehru Place 3 due for completion?
The completion date on record for Migsun Nehru Place 3 is 10 Oct 2028. Read it yourself against registration UPRERAPRJ585500/05/2024 on the UP-RERA portal, which is the authoritative source; this page is an independent mirror.
Who is the developer of Migsun Nehru Place 3?
Ansal It City & Parks Limited, which has 4 projects registered with UP-RERA.
Where can I verify Migsun Nehru Place 3's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ585500/05/2024. This page mirrors that public record for convenience.