Registration details
- Project name
- Intellicity @phase-3 Spine (Tower-A & B)
- RERA registration no.
- UPRERAPRJ11493
- Registration type
- Ongoing
- Registration date
- 15 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 31 Dec 2021 to 30 Jun 2022 over 1 registered extension.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 31 Dec 2021 | 30 Jun 2022 | +6mo | Six months extension in view of force... |
| Net slip vs first declared date | +6mo | to 30 Jun 2022 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Intellicity Business Park Private Limited
- Type
- Company
- Registered office
- Plot No - 10, Techzone-4, Greater Noida West, Uttar Pradesh
- Projects on the register
- 4
- Complaints · promoter-wide
- 102102 (Under Registration - 0 )
- Complaints · this project
- 56filed against Intellicity @phase-3...
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
22 documents filed on the UP-RERA portal for UPRERAPRJ11493. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Intellicity @Phase-3 Spine (Tower-A & B) RERA registered?
Yes. Intellicity @Phase-3 Spine (Tower-A & B) is registered with UP-RERA under registration number UPRERAPRJ11493, registered on 15 Aug 2017.
Is Intellicity @Phase-3 Spine (Tower-A & B) delayed?
Yes. It was declared for completion by 31 Dec 2021, but the date on record is now 30 Jun 2022, a slip of about 6 months across 1 registered extension.
Who is the developer of Intellicity @Phase-3 Spine (Tower-A & B)?
Intellicity Business Park Private Limited, which has 4 project(s) registered with UP-RERA and 102 complaint(s) on record across its projects.
How many complaints are filed against Intellicity @Phase-3 Spine (Tower-A & B)?
56 complaint(s) are recorded against Intellicity @Phase-3 Spine (Tower-A & B) specifically on the UP-RERA portal.
Where can I verify Intellicity @Phase-3 Spine (Tower-A & B)'s RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ11493. This page mirrors that public record for convenience.