Registration details
- Project name
- F Premiere (Phase 1)
- RERA registration no.
- UPRERAPRJ7115
- Registration type
- Ongoing
- Registration date
- 01 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarDadri
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 30 Jun 2021 to 31 Dec 2025 over 5 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 30 Jun 2021 | 29 Dec 2021 | +6mo | Six months extension in view of force... |
| 2 | 29 Dec 2021 | 28 Sep 2023 | +21mo | — |
| 3 | 28 Sep 2023 | 30 Sep 2024 | +12mo | — |
| 4 | 30 Sep 2024 | 31 Mar 2025 | +6mo | — |
| 5 | 31 Mar 2025 | 31 Dec 2025 | +9mo | — |
| Net slip vs first declared date | +54mo | to 31 Dec 2025 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Home And Soul Infratech Private Limited
- Type
- Company
- Registered office
- ASPIRE 2-701, SUPERTECH EMERALD COURT, SECTOR 93B, NOIDA, (U.P.)
- Projects on the register
- 4
- Complaints · promoter-wide
- 5353 (Under Registration - 2 )
- Complaints · this project
- 26filed against F Premiere (Phase 1)
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
14 documents filed on the UP-RERA portal for UPRERAPRJ7115. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is F Premiere (Phase 1) RERA registered?
Yes. F Premiere (Phase 1) is registered with UP-RERA under registration number UPRERAPRJ7115, registered on 01 Aug 2017.
Is F Premiere (Phase 1) delayed?
Yes. It was declared for completion by 30 Jun 2021, but the date on record is now 31 Dec 2025, a slip of about 54 months across 5 registered extensions.
Who is the developer of F Premiere (Phase 1)?
Home And Soul Infratech Private Limited, which has 4 project(s) registered with UP-RERA and 53 complaint(s) on record across its projects.
How many complaints are filed against F Premiere (Phase 1)?
26 complaint(s) are recorded against F Premiere (Phase 1) specifically on the UP-RERA portal.
Where can I verify F Premiere (Phase 1)'s RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ7115. This page mirrors that public record for convenience.