Ongoing 6-month delay UPRERAPRJ9325

Aastha Mig Zone I (M4 To M6)

by M/s Uttam Steels & Associates { Consortium) Throug · Dadri

Completion on record
30 Jun 2022
Declared 31 Dec 2021 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ9325
Gautam Buddha Nagar
Registered
12 Aug 2017
Type: Ongoing
Proposed period
81 mo
Declared completion
31 Dec 2021
original commitment
Latest on record
30 Jun 2022
after 1 extension
Documents on portal
23
filed with UP-RERA
01

Registration details

Project name
Aastha Mig Zone I (M4 To M6)
RERA registration no.
UPRERAPRJ9325
Registration type
Ongoing
Registration date
12 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarDadri
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 31 Dec 2021 to 30 Jun 2022 over 1 registered extension.

#FromToΔReason on record
131 Dec 202130 Jun 2022+6moSix months extension in view of force...
Net slip vs first declared date+6moto 30 Jun 2022

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
M/s Uttam Steels & Associates { Consortium) Throug
Type
Company
Registered office
115 Ansal Bhawan, 16 KG Marg, New Delhi-110001
Projects on the register
25
Complaints · promoter-wide
524524 (Under Registration - 1 )
Complaints · this project
19filed against Aastha Mig Zone I (M4 To M6)

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Aastha Mig Zone I (M4 To M6) RERA registered?

Yes. Aastha Mig Zone I (M4 To M6) is registered with UP-RERA under registration number UPRERAPRJ9325, registered on 12 Aug 2017.

Is Aastha Mig Zone I (M4 To M6) delayed?

Yes. It was declared for completion by 31 Dec 2021, but the date on record is now 30 Jun 2022, a slip of about 6 months across 1 registered extension.

Who is the developer of Aastha Mig Zone I (M4 To M6)?

M/S Uttam Steels & Associates { Consortium) Throug, which has 25 project(s) registered with UP-RERA and 524 complaint(s) on record across its projects.

How many complaints are filed against Aastha Mig Zone I (M4 To M6)?

19 complaint(s) are recorded against Aastha Mig Zone I (M4 To M6) specifically on the UP-RERA portal.

Where can I verify Aastha Mig Zone I (M4 To M6)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ9325. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Aastha Mig Zone I (M4 To M6). Straight answers, before you sign anything.