New 6-month delay UPRERAPRJ17623

Wtc Noida Cbd

by Wtc Noida Development Company Pvt Ltd · Gautam Buddha Nagar

Completion on record
26 Aug 2024
Declared 27 Feb 2024 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ17623
Gautam Buddha Nagar
Registered
19 Sep 2018
Type: New
Proposed period
60 mo
from 01 Oct 2018
Declared completion
27 Feb 2024
original commitment
Latest on record
26 Aug 2024
after 1 extension
Documents on portal
16
filed with UP-RERA
01

Registration details

Project name
Wtc Noida Cbd
RERA registration no.
UPRERAPRJ17623
Registration type
New
Registration date
19 Sep 2018
Proposed start
01 Oct 2018
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 27 Feb 2024 to 26 Aug 2024 over 1 registered extension.

#FromToΔReason on record
127 Feb 202426 Aug 2024+6moSix months extension in view of force...
Net slip vs first declared date+6moto 26 Aug 2024

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Wtc Noida Development Company Pvt Ltd
Type
Company
Registered office
GF09, M6 Plaza, Jasola, NEW DELHI - 110025
Projects on the register
1
Complaints · promoter-wide
826826 (Under Registration - 14 )
Complaints · this project
783filed against Wtc Noida Cbd

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Wtc Noida Cbd RERA registered?

Yes. Wtc Noida Cbd is registered with UP-RERA under registration number UPRERAPRJ17623, registered on 19 Sep 2018.

Is Wtc Noida Cbd delayed?

Yes. It was declared for completion by 27 Feb 2024, but the date on record is now 26 Aug 2024, a slip of about 6 months across 1 registered extension.

Who is the developer of Wtc Noida Cbd?

Wtc Noida Development Company Pvt Ltd, which has 1 project(s) registered with UP-RERA and 826 complaint(s) on record across its projects.

How many complaints are filed against Wtc Noida Cbd?

783 complaint(s) are recorded against Wtc Noida Cbd specifically on the UP-RERA portal.

Where can I verify Wtc Noida Cbd's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ17623. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Wtc Noida Cbd. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation