New 6-month delay UPRERAPRJ7325

Suntwilight - Recreational - Phase-Ii

by Sunrise Structures & Developers Private Limited · Gautam Buddha Nagar

Completion on record
14 Feb 2025
Declared 15 Aug 2024 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ7325
Gautam Buddha Nagar
Registered
02 Aug 2017
Type: New
Proposed period
84 mo
from 15 Aug 2017
Declared completion
15 Aug 2024
original commitment
Latest on record
14 Feb 2025
after 1 extension
Documents on portal
15
filed with UP-RERA
01

Registration details

Project name
Suntwilight - Recreational - Phase-Ii
RERA registration no.
UPRERAPRJ7325
Registration type
New
Registration date
02 Aug 2017
Proposed start
15 Aug 2017
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 15 Aug 2024 to 14 Feb 2025 over 1 registered extension.

#FromToΔReason on record
115 Aug 202414 Feb 2025+6moSix months extension in view of force...
Net slip vs first declared date+6moto 14 Feb 2025

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Sunrise Structures & Developers Private Limited
Type
Company
Registered office
R/o 59-A/19, 3D FLOOR, GURU NANAK PURA, LAXMI NAGAR, Delhi DL 110092 IN Project Site At REP-02A, Sector-27, Opp. Delta 1 Metro Station, Greater Noida U P -201308
Projects on the register
3
Complaints · promoter-wide
22 (Under Registration - 0 )
Complaints · this project
0filed against Suntwilight -...

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Suntwilight - Recreational - Phase-Ii RERA registered?

Yes. Suntwilight - Recreational - Phase-Ii is registered with UP-RERA under registration number UPRERAPRJ7325, registered on 02 Aug 2017.

Is Suntwilight - Recreational - Phase-Ii delayed?

Yes. It was declared for completion by 15 Aug 2024, but the date on record is now 14 Feb 2025, a slip of about 6 months across 1 registered extension.

Who is the developer of Suntwilight - Recreational - Phase-Ii?

Sunrise Structures & Developers Private Limited, which has 3 project(s) registered with UP-RERA and 2 complaint(s) on record across its projects.

How many complaints are filed against Suntwilight - Recreational - Phase-Ii?

0 complaint(s) are recorded against Suntwilight - Recreational - Phase-Ii specifically on the UP-RERA portal.

Where can I verify Suntwilight - Recreational - Phase-Ii's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ7325. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Suntwilight - Recreational - Phase-Ii. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation