New 12-month delay UPRERAPRJ17035

Spectrum Metro

by Blue Square Infrastructure Llp · Gautam Buddha Nagar

Completion on record
02 Nov 2024
Declared 01 Nov 2023 · slipped 12 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ17035
Gautam Buddha Nagar
Registered
16 Jul 2018
Type: New
Proposed period
61 mo
from 01 Nov 2018
Declared completion
01 Nov 2023
original commitment
Latest on record
02 Nov 2024
after 2 extensions
Documents on portal
15
filed with UP-RERA
01

Registration details

Project name
Spectrum Metro
RERA registration no.
UPRERAPRJ17035
Registration type
New
Registration date
16 Jul 2018
Proposed start
01 Nov 2018
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+12months later than promised

Declared completion moved from 01 Nov 2023 to 02 Nov 2024 over 2 registered extensions.

#FromToΔReason on record
101 Nov 202330 Apr 2024+5moSix months extension in view of force...
230 Apr 202402 Nov 2024+7mo
Net slip vs first declared date+12moto 02 Nov 2024

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Blue Square Infrastructure Llp
Type
Partnership Firm
Registered office
Unit-219 S/F Vasundhara Enclave, Plot No. 1, Vardhman Sunrise Plaza LSC, New Delhi-110096
Projects on the register
6
Complaints · promoter-wide
4949 (Under Registration - 4 )
Complaints · this project
13filed against Spectrum Metro

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Spectrum Metro RERA registered?

Yes. Spectrum Metro is registered with UP-RERA under registration number UPRERAPRJ17035, registered on 16 Jul 2018.

Is Spectrum Metro delayed?

Yes. It was declared for completion by 01 Nov 2023, but the date on record is now 02 Nov 2024, a slip of about 12 months across 2 registered extensions.

Who is the developer of Spectrum Metro?

Blue Square Infrastructure Llp, which has 6 project(s) registered with UP-RERA and 49 complaint(s) on record across its projects.

How many complaints are filed against Spectrum Metro?

13 complaint(s) are recorded against Spectrum Metro specifically on the UP-RERA portal.

Where can I verify Spectrum Metro's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ17035. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Spectrum Metro. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation