Registration details
- Project name
- Sikka Kaamya Greens
- RERA registration no.
- UPRERAPRJ5790
- Registration type
- Ongoing
- Registration date
- 04 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 30 Jun 2021 to 30 Apr 2026 over 3 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 30 Jun 2021 | 29 Dec 2021 | +6mo | Six months extension in view of force... |
| 2 | 29 Dec 2021 | 28 Sep 2023 | +21mo | — |
| 3 | 28 Sep 2023 | 30 Apr 2026 | +31mo | — |
| Net slip vs first declared date | +58mo | to 30 Apr 2026 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Eco Green Buildtech Private Limited
- Type
- Company
- Registered office
- C-60 PREET VIHAR
- Projects on the register
- 1
- Complaints · promoter-wide
- 119119 (Under Registration - 1 )
- Complaints · this project
- 116filed against Sikka Kaamya Greens
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
15 documents filed on the UP-RERA portal for UPRERAPRJ5790. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Sikka Kaamya Greens RERA registered?
Yes. Sikka Kaamya Greens is registered with UP-RERA under registration number UPRERAPRJ5790, registered on 04 Aug 2017.
Is Sikka Kaamya Greens delayed?
Yes. It was declared for completion by 30 Jun 2021, but the date on record is now 30 Apr 2026, a slip of about 58 months across 3 registered extensions.
Who is the developer of Sikka Kaamya Greens?
Eco Green Buildtech Private Limited, which has 1 project(s) registered with UP-RERA and 119 complaint(s) on record across its projects.
How many complaints are filed against Sikka Kaamya Greens?
116 complaint(s) are recorded against Sikka Kaamya Greens specifically on the UP-RERA portal.
Where can I verify Sikka Kaamya Greens's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ5790. This page mirrors that public record for convenience.
Want to go through this file before you commit?
Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Sikka Kaamya Greens. Straight answers, before you sign anything.
Private line · no obligation