Ongoing 58-month delay UPRERAPRJ5790

Sikka Kaamya Greens

by Eco Green Buildtech Private Limited · Gautam Buddha Nagar

Completion on record
30 Apr 2026
Declared 30 Jun 2021 · slipped 58 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ5790
Gautam Buddha Nagar
Registered
04 Aug 2017
Type: Ongoing
Proposed period
77 mo
Declared completion
30 Jun 2021
original commitment
Latest on record
30 Apr 2026
after 3 extensions
Documents on portal
15
filed with UP-RERA
01

Registration details

Project name
Sikka Kaamya Greens
RERA registration no.
UPRERAPRJ5790
Registration type
Ongoing
Registration date
04 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+58months later than promised

Declared completion moved from 30 Jun 2021 to 30 Apr 2026 over 3 registered extensions.

#FromToΔReason on record
130 Jun 202129 Dec 2021+6moSix months extension in view of force...
229 Dec 202128 Sep 2023+21mo
328 Sep 202330 Apr 2026+31mo
Net slip vs first declared date+58moto 30 Apr 2026

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Eco Green Buildtech Private Limited
Type
Company
Registered office
C-60 PREET VIHAR
Projects on the register
1
Complaints · promoter-wide
119119 (Under Registration - 1 )
Complaints · this project
116filed against Sikka Kaamya Greens

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Sikka Kaamya Greens RERA registered?

Yes. Sikka Kaamya Greens is registered with UP-RERA under registration number UPRERAPRJ5790, registered on 04 Aug 2017.

Is Sikka Kaamya Greens delayed?

Yes. It was declared for completion by 30 Jun 2021, but the date on record is now 30 Apr 2026, a slip of about 58 months across 3 registered extensions.

Who is the developer of Sikka Kaamya Greens?

Eco Green Buildtech Private Limited, which has 1 project(s) registered with UP-RERA and 119 complaint(s) on record across its projects.

How many complaints are filed against Sikka Kaamya Greens?

116 complaint(s) are recorded against Sikka Kaamya Greens specifically on the UP-RERA portal.

Where can I verify Sikka Kaamya Greens's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ5790. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Sikka Kaamya Greens. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation