Ongoing 21-month delay UPRERAPRJ6440

Raj Hans Residency (Phase-1)

by Raj Hans Infratech Private Limited · Gautam Buddha Nagar

Completion on record
30 Sep 2021
Declared 31 Dec 2019 · slipped 21 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ6440
Gautam Buddha Nagar
Registered
12 Aug 2017
Type: Ongoing
Proposed period
72 mo
Declared completion
31 Dec 2019
original commitment
Latest on record
30 Sep 2021
after 3 extensions
Documents on portal
28
filed with UP-RERA
01

Registration details

Project name
Raj Hans Residency (Phase-1)
RERA registration no.
UPRERAPRJ6440
Registration type
Ongoing
Registration date
12 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+21months later than promised

Declared completion moved from 31 Dec 2019 to 30 Sep 2021 over 3 registered extensions.

#FromToΔReason on record
131 Dec 201930 Dec 2020+12mo
230 Dec 202029 Jun 2021+6moSix months extension in view of force...
329 Jun 202130 Sep 2021+3mo
Net slip vs first declared date+21moto 30 Sep 2021

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Raj Hans Infratech Private Limited
Type
Company
Registered office
Registered Office Address- M-33, 2nd Floor, Greater Kailash, Part - I, New Delhi 110048, Corporate Office Address- M-33, 2nd Floor, Greater Kailash, Part - I, New Delhi 110048, Site Address- Plot No. GH-06B, Sector-1, Greater NOIDA (West), Gautam Buddha Nagar, UP.
Projects on the register
2
Complaints · promoter-wide
1919 (Under Registration - 0 )
Complaints · this project
10filed against Raj Hans Residency (Phase-1)

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Raj Hans Residency (Phase-1) RERA registered?

Yes. Raj Hans Residency (Phase-1) is registered with UP-RERA under registration number UPRERAPRJ6440, registered on 12 Aug 2017.

Is Raj Hans Residency (Phase-1) delayed?

Yes. It was declared for completion by 31 Dec 2019, but the date on record is now 30 Sep 2021, a slip of about 21 months across 3 registered extensions.

Who is the developer of Raj Hans Residency (Phase-1)?

Raj Hans Infratech Private Limited, which has 2 project(s) registered with UP-RERA and 19 complaint(s) on record across its projects.

How many complaints are filed against Raj Hans Residency (Phase-1)?

10 complaint(s) are recorded against Raj Hans Residency (Phase-1) specifically on the UP-RERA portal.

Where can I verify Raj Hans Residency (Phase-1)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ6440. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Raj Hans Residency (Phase-1). Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation