Registration details
- Project name
- Presidential Villas
- RERA registration no.
- UPRERAPRJ13203
- Registration type
- New
- Registration date
- 28 Sep 2017
- Proposed start
- 01 Oct 2019
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 30 Sep 2023 to 29 Mar 2024 over 1 registered extension.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 30 Sep 2023 | 29 Mar 2024 | +6mo | Six months extension in view of force... |
| Net slip vs first declared date | +6mo | to 29 Mar 2024 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Ar Landcraft Llp
- Type
- Limited Liability Partnership (LLP)
- Registered office
- UM House, 3rd Floor, Plot No. 35P, UM House, Sector-44, Gurgaon, Haryana – 122002
- Projects on the register
- 9
- Complaints · promoter-wide
- 235235 (Under Registration - 5 )
- Complaints · this project
- 8filed against Presidential Villas
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
62 documents filed on the UP-RERA portal for UPRERAPRJ13203. Each opens on the official portal record.
More from Ar Landcraft Llp
Other projects nearby
Frequently asked
Is Presidential Villas RERA registered?
Yes. Presidential Villas is registered with UP-RERA under registration number UPRERAPRJ13203, registered on 28 Sep 2017.
Is Presidential Villas delayed?
Yes. It was declared for completion by 30 Sep 2023, but the date on record is now 29 Mar 2024, a slip of about 6 months across 1 registered extension.
Who is the developer of Presidential Villas?
Ar Landcraft Llp, which has 9 project(s) registered with UP-RERA and 235 complaint(s) on record across its projects.
How many complaints are filed against Presidential Villas?
8 complaint(s) are recorded against Presidential Villas specifically on the UP-RERA portal.
Where can I verify Presidential Villas's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ13203. This page mirrors that public record for convenience.
Want to go through this file before you commit?
Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Presidential Villas. Straight answers, before you sign anything.