Registration details
- Project name
- Novena Green
- RERA registration no.
- UPRERAPRJ8646
- Registration type
- Ongoing
- Registration date
- 12 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 31 Oct 2018 to 30 Jun 2027 over 2 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 31 Oct 2018 | 31 Oct 2019 | +12mo | — |
| 2 | 31 Oct 2019 | 30 Jun 2027 | +92mo | — |
| Net slip vs first declared date | +104mo | to 30 Jun 2027 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- D S D Homes Private Limited
- Type
- Company
- Registered office
- PLOT NO. CP-GH-05-B, TECH ZONE-IV, GREATER NOIDA WEST, GAUTAM BUDH NAGAR, UP
- Projects on the register
- 1
- Complaints · promoter-wide
- 116116 (Under Registration - 0 )
- Complaints · this project
- 110filed against Novena Green
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
19 documents filed on the UP-RERA portal for UPRERAPRJ8646. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Novena Green RERA registered?
Yes. Novena Green is registered with UP-RERA under registration number UPRERAPRJ8646, registered on 12 Aug 2017.
Is Novena Green delayed?
Yes. It was declared for completion by 31 Oct 2018, but the date on record is now 30 Jun 2027, a slip of about 104 months across 2 registered extensions.
Who is the developer of Novena Green?
D S D Homes Private Limited, which has 1 project(s) registered with UP-RERA and 116 complaint(s) on record across its projects.
How many complaints are filed against Novena Green?
110 complaint(s) are recorded against Novena Green specifically on the UP-RERA portal.
Where can I verify Novena Green's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ8646. This page mirrors that public record for convenience.