Registration details
- Project name
- Mahagun Manorial
- RERA registration no.
- UPRERAPRJ2051
- Registration type
- Ongoing
- Registration date
- 27 Jul 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Sector 128, Noida
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 31 Dec 2021 to 30 Jun 2027 over 3 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 31 Dec 2021 | 30 Jun 2022 | +6mo | Six months extension in view of force... |
| 2 | 30 Jun 2022 | 29 Mar 2024 | +21mo | — |
| 3 | 29 Mar 2024 | 30 Jun 2027 | +39mo | — |
| Net slip vs first declared date | +66mo | to 30 Jun 2027 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Mahagun (India) Pvt. Ltd.
- Type
- Company
- Registered office
- A-19, Sector-63, Noida, Uttar Pradesh-201301
- Projects on the register
- 5
- Complaints · promoter-wide
- 368368 (Under Registration - 3 )
- Complaints · this project
- 16filed against Mahagun Manorial
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
104 documents filed on the UP-RERA portal for UPRERAPRJ2051. Each opens on the official portal record.
More from Mahagun (India) Pvt. Ltd.
Other projects nearby
Frequently asked
Is Mahagun Manorial RERA registered?
Yes. Mahagun Manorial is registered with UP-RERA under registration number UPRERAPRJ2051, registered on 27 Jul 2017.
Is Mahagun Manorial delayed?
Yes. It was declared for completion by 31 Dec 2021, but the date on record is now 30 Jun 2027, a slip of about 66 months across 3 registered extensions.
Who is the developer of Mahagun Manorial?
Mahagun (India) Pvt. Ltd., which has 5 project(s) registered with UP-RERA and 368 complaint(s) on record across its projects.
How many complaints are filed against Mahagun Manorial?
16 complaint(s) are recorded against Mahagun Manorial specifically on the UP-RERA portal.
Where can I verify Mahagun Manorial's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ2051. This page mirrors that public record for convenience.