Ongoing 56-month delay UPRERAPRJ4695

Jaypee Greens Kalypso Court (Phase Ii), Noida

by Jaiprakash Associates Limited · Gautam Buddha Nagar

Completion on record
28 Feb 2023
Declared 30 Jun 2018 · slipped 56 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ4695
Gautam Buddha Nagar
Registered
29 Jul 2017
Type: Ongoing
Proposed period
125 mo
Declared completion
30 Jun 2018
original commitment
Latest on record
28 Feb 2023
after 2 extensions
Documents on portal
21
filed with UP-RERA
01

Registration details

Project name
Jaypee Greens Kalypso Court (Phase Ii), Noida
RERA registration no.
UPRERAPRJ4695
Registration type
Ongoing
Registration date
29 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+56months later than promised

Declared completion moved from 30 Jun 2018 to 28 Feb 2023 over 2 registered extensions.

#FromToΔReason on record
130 Jun 201830 Jan 2022+43mo
230 Jan 202228 Feb 2023+13mo
Net slip vs first declared date+56moto 28 Feb 2023

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Jaiprakash Associates Limited
Type
Company
Registered office
Sector - 128, Noida - 201304, Uttar Pradesh (India)
Projects on the register
42
Complaints · promoter-wide
13471347 (Under Registration - 1 )
Complaints · this project
32filed against Jaypee Greens...

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Jaypee Greens Kalypso Court (Phase Ii), Noida RERA registered?

Yes. Jaypee Greens Kalypso Court (Phase Ii), Noida is registered with UP-RERA under registration number UPRERAPRJ4695, registered on 29 Jul 2017.

Is Jaypee Greens Kalypso Court (Phase Ii), Noida delayed?

Yes. It was declared for completion by 30 Jun 2018, but the date on record is now 28 Feb 2023, a slip of about 56 months across 2 registered extensions.

Who is the developer of Jaypee Greens Kalypso Court (Phase Ii), Noida?

Jaiprakash Associates Limited, which has 42 project(s) registered with UP-RERA and 1347 complaint(s) on record across its projects.

How many complaints are filed against Jaypee Greens Kalypso Court (Phase Ii), Noida?

32 complaint(s) are recorded against Jaypee Greens Kalypso Court (Phase Ii), Noida specifically on the UP-RERA portal.

Where can I verify Jaypee Greens Kalypso Court (Phase Ii), Noida's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ4695. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Jaypee Greens Kalypso Court (Phase Ii), Noida. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation