New No extensions UPRERAPRJ794300/09/2025

Green Reserve Tower 3 And 4

by Larsen & Toubro Limited · Dadri

Completion on record
28 May 2028
Declared at registration · no extensions filed
Speak with an advisor
Green Reserve Tower 3 And 4, project image
Builder marketing render via 360propguide.com, a promotional image, not a UP-RERA record.
Overview Land & costProgressLocationEscrowTeamDevelopment Promoter Documents FAQ
RERA number
UPRERAPRJ794300/09/2025
Gautam Buddha Nagar
Registered
02 Sep 2025
Type: New
Proposed period
72 mo
from 28 Dec 2023
Declared completion
28 May 2028
original commitment
Latest on record
28 May 2028
unchanged
Documents on portal
17
filed with UP-RERA
01

Registration details

Project name
Green Reserve Tower 3 And 4
RERA registration no.
UPRERAPRJ794300/09/2025
Registration type
New
Registration date
02 Sep 2025
Proposed start
28 Dec 2023
District / tehsil
Gautam Buddha NagarDadri
Project address
Not stated on the register
Record source
up-rera.in
02

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Larsen & Toubro Limited
Type
Company
Registered office
L&T House, N. M. Marg, Ballard Estate, Mumbai - 400 001
Projects on the register
2
Complaints · promoter-wide
11 (Under Registration - 1 )
Complaints · this project
0filed against Green Reserve Tower 3 And 4

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

04

Land, build & cost

Transcribed from this project's certificates (CA, architect, engineer and development filings) on the UP-RERA portal. Figures are on the public record; verify at up-rera.in before acting.

View the source certificate (PDF) →
Land area
3.04 ac
12,311 m²
Project size
2.0 bldgs
Project cost
₹964 Cr
construction ₹656 Cr
Cost incurred
₹288 Cr
29.8% of estimated cost
05

Construction progress

How far the money and the build clock have moved, from the certified figures on the project's filings. View the source certificate (PDF) →

Certified spend30%
of the estimated project cost, certified spent to date
Build clock59%
of the registered build period elapsed
Physical build1%
of construction complete, per the engineer's certificate

The build clock is running ahead of certified spend: 59% of the registered timeline has passed, but only 30% of the budget is certified spent. A gap worth asking the promoter about.

A snapshot from certified filings, not a live feed; the build clock is computed from the registered start and current completion date. Verify at up-rera.in.

06

Location

Coordinates and site details as filed on the project's certificate. View the source certificate (PDF) →

Coordinates
28.525767, 77.361167
07

Bank account

The collection account into which buyers deposit, as named on the project's certificate filed with UP-RERA. View the source certificate (PDF) →

Collection account
A/c no. 777705003236
08

Project team

The consultants named on the project's architect and engineer certificates. View the source certificate (PDF) →

Architect
SWAPNA DIPANKAR NATHLicence CA/2005/36281
Structural engineer
VINOD K TIKUTHE INSTITUTION OF ENGINEERS (INDIA)
09

Development & infrastructure

Committed works as stated in the project's development affidavit on the portal. View the source certificate (PDF) →

Sewage treatment plant (STP)
Installation and external development
Electric supply
General electrical works
Fire safety
Fire fighting system installation
Staircases
Construction of R2 Staircases (B1 to F4)
Roads
Construction
Parks / Landscaping
Development and finishing
12

Frequently asked

Is Green Reserve Tower 3 And 4 RERA registered?

Yes. Green Reserve Tower 3 And 4 is registered with UP-RERA under registration number UPRERAPRJ794300/09/2025, registered on 02 Sep 2025.

What is the RERA completion date for Green Reserve Tower 3 And 4?

The completion date on record is 28 May 2028, with no extensions filed against the original commitment.

Who is the developer of Green Reserve Tower 3 And 4?

Larsen & Toubro Limited, which has 2 project(s) registered with UP-RERA and 1 complaint(s) on record across its projects.

How many complaints are filed against Green Reserve Tower 3 And 4?

0 complaint(s) are recorded against Green Reserve Tower 3 And 4 specifically on the UP-RERA portal.

Where can I verify Green Reserve Tower 3 And 4's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ794300/09/2025. This page mirrors that public record for convenience.