Ongoing 77-month delay UPRERAPRJ5929

Antriksh Valley

by Diligent Builders Pvt. Ltd. (Antriksh Group) · Gautam Buddha Nagar

Completion on record
31 Dec 2027
Declared 26 Jul 2021 · slipped 77 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ5929
Gautam Buddha Nagar
Registered
13 Aug 2017
Type: Ongoing
Proposed period
96 mo
Declared completion
26 Jul 2021
original commitment
Latest on record
31 Dec 2027
after 2 extensions
Documents on portal
19
filed with UP-RERA
01

Registration details

Project name
Antriksh Valley
RERA registration no.
UPRERAPRJ5929
Registration type
Ongoing
Registration date
13 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+77months later than promised

Declared completion moved from 26 Jul 2021 to 31 Dec 2027 over 2 registered extensions.

#FromToΔReason on record
126 Jul 202125 Jan 2022+6moSix months extension in view of force...
225 Jan 202231 Dec 2027+71mo
Net slip vs first declared date+77moto 31 Dec 2027

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Diligent Builders Pvt. Ltd. (Antriksh Group)
Type
Company
Registered office
34/C-8, SECTOR-8, ROHINI, NEW DELHI - 110085.
Projects on the register
1
Complaints · promoter-wide
5555 (Under Registration - 0 )
Complaints · this project
49filed against Antriksh Valley

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Antriksh Valley RERA registered?

Yes. Antriksh Valley is registered with UP-RERA under registration number UPRERAPRJ5929, registered on 13 Aug 2017.

Is Antriksh Valley delayed?

Yes. It was declared for completion by 26 Jul 2021, but the date on record is now 31 Dec 2027, a slip of about 77 months across 2 registered extensions.

Who is the developer of Antriksh Valley?

Diligent Builders Pvt. Ltd. (Antriksh Group), which has 1 project(s) registered with UP-RERA and 55 complaint(s) on record across its projects.

How many complaints are filed against Antriksh Valley?

49 complaint(s) are recorded against Antriksh Valley specifically on the UP-RERA portal.

Where can I verify Antriksh Valley's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ5929. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Antriksh Valley. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation