Ongoing 6-month delay UPRERAPRJ10510

Antriksh Golf Link Phase 2

by M/s Antriksh Engineers Private Limited ( Antriksh · Gautam Buddha Nagar

Completion on record
24 Nov 2021
Declared 25 May 2021 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ10510
Gautam Buddha Nagar
Registered
14 Aug 2017
Type: Ongoing
Proposed period
120 mo
Declared completion
25 May 2021
original commitment
Latest on record
24 Nov 2021
after 1 extension
Documents on portal
16
filed with UP-RERA
01

Registration details

Project name
Antriksh Golf Link Phase 2
RERA registration no.
UPRERAPRJ10510
Registration type
Ongoing
Registration date
14 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 25 May 2021 to 24 Nov 2021 over 1 registered extension.

#FromToΔReason on record
125 May 202124 Nov 2021+6moSix months extension in view of force...
Net slip vs first declared date+6moto 24 Nov 2021

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
M/s Antriksh Engineers Private Limited ( Antriksh
Type
Company
Registered office
34/C-8, SECTOR-8, ROHINI, NEW DELHI - 110085
Projects on the register
4
Complaints · promoter-wide
127127 (Under Registration - 1 )
Complaints · this project
16filed against Antriksh Golf Link Phase 2

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Antriksh Golf Link Phase 2 RERA registered?

Yes. Antriksh Golf Link Phase 2 is registered with UP-RERA under registration number UPRERAPRJ10510, registered on 14 Aug 2017.

Is Antriksh Golf Link Phase 2 delayed?

Yes. It was declared for completion by 25 May 2021, but the date on record is now 24 Nov 2021, a slip of about 6 months across 1 registered extension.

Who is the developer of Antriksh Golf Link Phase 2?

M/S Antriksh Engineers Private Limited ( Antriksh, which has 4 project(s) registered with UP-RERA and 127 complaint(s) on record across its projects.

How many complaints are filed against Antriksh Golf Link Phase 2?

16 complaint(s) are recorded against Antriksh Golf Link Phase 2 specifically on the UP-RERA portal.

Where can I verify Antriksh Golf Link Phase 2's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ10510. This page mirrors that public record for convenience.