Ongoing 16-month delay UPRERAPRJ3058

Ajnara Panorama (Phase-3 Studio & Convinient Shops

by Ajnara India Limited · Gautam Buddha Nagar

Completion on record
06 Dec 2021
Declared 31 Aug 2020 · slipped 16 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ3058
Gautam Buddha Nagar
Registered
28 Jul 2017
Type: Ongoing
Proposed period
91 mo
Declared completion
31 Aug 2020
original commitment
Latest on record
06 Dec 2021
after 2 extensions
Documents on portal
29
filed with UP-RERA
01

Registration details

Project name
Ajnara Panorama (Phase-3 Studio & Convinient Shops
RERA registration no.
UPRERAPRJ3058
Registration type
Ongoing
Registration date
28 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+16months later than promised

Declared completion moved from 31 Aug 2020 to 06 Dec 2021 over 2 registered extensions.

#FromToΔReason on record
131 Aug 202028 Feb 2021+6moSix months extension in view of force...
228 Feb 202106 Dec 2021+10mo
Net slip vs first declared date+16moto 06 Dec 2021

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Ajnara India Limited
Type
Company
Registered office
1. B-189, YOJNA VIHAR, DELHI-92 2. B-189, YOJNA VIHAR, DELHI-92 3. B-189, YOJNA VIHAR, DELHI-92 4
Projects on the register
13
Complaints · promoter-wide
342342 (Under Registration - 0 )
Complaints · this project
15filed against Ajnara Panorama...

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Ajnara Panorama (Phase-3 Studio & Convinient Shops RERA registered?

Yes. Ajnara Panorama (Phase-3 Studio & Convinient Shops is registered with UP-RERA under registration number UPRERAPRJ3058, registered on 28 Jul 2017.

Is Ajnara Panorama (Phase-3 Studio & Convinient Shops delayed?

Yes. It was declared for completion by 31 Aug 2020, but the date on record is now 06 Dec 2021, a slip of about 16 months across 2 registered extensions.

Who is the developer of Ajnara Panorama (Phase-3 Studio & Convinient Shops?

Ajnara India Limited, which has 13 project(s) registered with UP-RERA and 342 complaint(s) on record across its projects.

How many complaints are filed against Ajnara Panorama (Phase-3 Studio & Convinient Shops?

15 complaint(s) are recorded against Ajnara Panorama (Phase-3 Studio & Convinient Shops specifically on the UP-RERA portal.

Where can I verify Ajnara Panorama (Phase-3 Studio & Convinient Shops's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ3058. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Ajnara Panorama (Phase-3 Studio & Convinient Shops. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation