Ongoing 6-month delay UPRERAPRJ6332

Gulshan Bellina

by Gulshan Homz Private Limited · Gautam Buddha Nagar

Completion on record
02 Jul 2022
Declared 03 Jan 2022 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ6332
Gautam Buddha Nagar
Registered
31 Jul 2017
Type: Ongoing
Proposed period
72 mo
Declared completion
03 Jan 2022
original commitment
Latest on record
02 Jul 2022
after 1 extension
Documents on portal
31
filed with UP-RERA
01

Registration details

Project name
Gulshan Bellina
RERA registration no.
UPRERAPRJ6332
Registration type
Ongoing
Registration date
31 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 03 Jan 2022 to 02 Jul 2022 over 1 registered extension.

#FromToΔReason on record
103 Jan 202202 Jul 2022+6moSix months extension in view of force...
Net slip vs first declared date+6moto 02 Jul 2022

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Gulshan Homz Private Limited
Type
Company
Registered office
121,Hargovind Enclave, Delhi 110092
Projects on the register
3
Complaints · promoter-wide
3939 (Under Registration - 0 )
Complaints · this project
27filed against Gulshan Bellina

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Gulshan Bellina RERA registered?

Yes. Gulshan Bellina is registered with UP-RERA under registration number UPRERAPRJ6332, registered on 31 Jul 2017.

Is Gulshan Bellina delayed?

Yes. It was declared for completion by 03 Jan 2022, but the date on record is now 02 Jul 2022, a slip of about 6 months across 1 registered extension.

Who is the developer of Gulshan Bellina?

Gulshan Homz Private Limited, which has 3 project(s) registered with UP-RERA and 39 complaint(s) on record across its projects.

How many complaints are filed against Gulshan Bellina?

27 complaint(s) are recorded against Gulshan Bellina specifically on the UP-RERA portal.

Where can I verify Gulshan Bellina's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ6332. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Gulshan Bellina. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation