How many projects on the register are delayed?
519 of the 966 UP-RERA-registered projects in Gautam Buddha Nagar, 54%, carry a completion-date extension that has actually pushed the finish date later. A further 7 projects have an extension entry on file where the recorded dates show no net move, so 526 of 966 carry at least one extension in total; 519 of those show a real slip. The rest, 440 of 966, have never revised their declared completion date at all.
What does "delayed" mean on this site, exactly?
It means two things are both true on the register: at least one completion-date extension has been filed, and the date now on file is later than what was declared when the project was first registered. That's a mechanical read of two dates, not a judgment call. Every project page on this site shows both dates, the size of the slip in months, and the number of extensions filed, so the read is checkable against the underlying record for any project on it.
How many times has a typical delayed project revised its date?
Most delayed projects have moved their date once: of the 526 registrations with at least one extension on file, 320 have exactly one, 124 have two, and 55 have three. A smaller group has revised the date four times (19 projects), five times (5) or six times (3), each additional entry its own filed record on the register, not one blanket change.
| Extensions filed | Projects |
|---|---|
| 0 | 440 |
| 1 | 320 |
| 2 | 124 |
| 3 | 55 |
| 4 | 19 |
| 5 | 5 |
| 6 | 3 |
Which projects show the largest gap between declared and current date?
Ranked by the size of the slip in months, largest first, these are the 15 largest completion-date moves on the Gautam Buddha Nagar register today. A large slip is a fact worth asking about; on its own it is not proof of why the date moved.
| Project | Promoter | Area | Ext. | Slip | Declared → latest |
|---|---|---|---|---|---|
| Morpheus Pratiksha | Morpheus Developers Pvt Ltd | Noida | 1 | 122 mo | 31 Dec 2019 → 06 Feb 2030 |
| Mayfair Residency | Super City Developers Pvt Ltd | Noida | 2 | 120 mo | 31 Dec 2018 → 31 Dec 2028 |
| JMDR Arihant Green | Bliss Town Developers Private Limited | Greater Noida | 1 | 108 mo | 30 Dec 2018 → 31 Dec 2027 |
| Novena Green | DSD Homes Private Limited | Noida | 2 | 104 mo | 31 Oct 2018 → 30 Jun 2027 |
| Green View II | Green View-II Sahakari Awas Samiti Limited | Noida | 2 | 102 mo | 31 Dec 2019 → 30 Jun 2028 |
| Sunworld Arista (Phase 2) | Sunworld Residency Private Limited | Noida | 2 | 97 mo | 31 Dec 2021 → 23 Jan 2030 |
| Skytech Colours Avenue | Jatasya Promoters Pvt Ltd | Noida | 5 | 94 mo | 10 Oct 2020 → 20 Aug 2028 |
| Jaypee Greens Kosmos C, Noida | Jaypee Infratech Limited | Noida | 1 | 93 mo | 31 Dec 2018 → 29 Sep 2026 |
| Shivalik Homes 2 | Cosmos Infraestate Pvt. Ltd. | Noida | 2 | 93 mo | 31 Mar 2021 → 31 Dec 2028 |
| Future Estate (Phase 1) | Futureworld Greenhomes Pvt. Ltd. | Noida | 6 | 91 mo | 31 Dec 2018 → 31 Jul 2026 |
| Jaypee Greens Kasa Isles, Noida | Jaypee Infratech Limited | Noida | 2 | 91 mo | 31 Mar 2020 → 09 Oct 2027 |
| Rhythm County (Phase 2) | Futureworld Greenhomes Pvt. Ltd. | Noida | 5 | 91 mo | 31 Dec 2019 → 31 Jul 2027 |
| Rhythm County (Phase 1) | Futureworld Greenhomes Pvt. Ltd. | Greater Noida | 6 | 91 mo | 31 Dec 2018 → 31 Jul 2026 |
| Jaypee Greens Kosmos A (Phase 2), Noida | Jaypee Infratech Limited | Noida | 1 | 90 mo | 31 Mar 2019 → 29 Sep 2026 |
| KVD Windpark | KV Developers Private Limited | Noida | 2 | 89 mo | 07 Oct 2021 → 10 Mar 2029 |
How to read one project's full extension history
Open any delayed project's page and its completion-date section lays out every step: the originally declared date, then each extension in sequence with the revised date and the months it added, ending at the date currently on file. The same information sits in a dated table further down the page, extension by extension, so nothing about the timeline has to be inferred or taken on faith.
What a delayed listing does not tell you
A slip of a given size doesn't say why the date moved, whether the promoter is otherwise reliable, or how the current pace of construction compares to what's left on the clock. Read what an extension does and doesn't establish first, then weigh it against the promoter's wider record. Confirm the number on up-rera.in before treating anything here as final: this page mirrors that record, it isn't the record.