The delayed-projects ledger: how far Gautam Buddha Nagar's registrations have actually slipped

519 of the 966 UP-RERA projects on record here carry a completion-date extension that moved the finish date later. This is the register's own worst-first list, what an extension does and doesn't establish, and how to read one project's full history.

How many projects on the register are delayed?

519 of the 966 UP-RERA-registered projects in Gautam Buddha Nagar, 54%, carry a completion-date extension that has actually pushed the finish date later. A further 7 projects have an extension entry on file where the recorded dates show no net move, so 526 of 966 carry at least one extension in total; 519 of those show a real slip. The rest, 440 of 966, have never revised their declared completion date at all.

What does "delayed" mean on this site, exactly?

It means two things are both true on the register: at least one completion-date extension has been filed, and the date now on file is later than what was declared when the project was first registered. That's a mechanical read of two dates, not a judgment call. Every project page on this site shows both dates, the size of the slip in months, and the number of extensions filed, so the read is checkable against the underlying record for any project on it.

How many times has a typical delayed project revised its date?

Most delayed projects have moved their date once: of the 526 registrations with at least one extension on file, 320 have exactly one, 124 have two, and 55 have three. A smaller group has revised the date four times (19 projects), five times (5) or six times (3), each additional entry its own filed record on the register, not one blanket change.

Extensions filedProjects
0440
1320
2124
355
419
55
63

Which projects show the largest gap between declared and current date?

Ranked by the size of the slip in months, largest first, these are the 15 largest completion-date moves on the Gautam Buddha Nagar register today. A large slip is a fact worth asking about; on its own it is not proof of why the date moved.

ProjectPromoterAreaExt.SlipDeclared → latest
Morpheus PratikshaMorpheus Developers Pvt LtdNoida1122 mo31 Dec 2019 → 06 Feb 2030
Mayfair ResidencySuper City Developers Pvt LtdNoida2120 mo31 Dec 2018 → 31 Dec 2028
JMDR Arihant GreenBliss Town Developers Private LimitedGreater Noida1108 mo30 Dec 2018 → 31 Dec 2027
Novena GreenDSD Homes Private LimitedNoida2104 mo31 Oct 2018 → 30 Jun 2027
Green View IIGreen View-II Sahakari Awas Samiti LimitedNoida2102 mo31 Dec 2019 → 30 Jun 2028
Sunworld Arista (Phase 2)Sunworld Residency Private LimitedNoida297 mo31 Dec 2021 → 23 Jan 2030
Skytech Colours AvenueJatasya Promoters Pvt LtdNoida594 mo10 Oct 2020 → 20 Aug 2028
Jaypee Greens Kosmos C, NoidaJaypee Infratech LimitedNoida193 mo31 Dec 2018 → 29 Sep 2026
Shivalik Homes 2Cosmos Infraestate Pvt. Ltd.Noida293 mo31 Mar 2021 → 31 Dec 2028
Future Estate (Phase 1)Futureworld Greenhomes Pvt. Ltd.Noida691 mo31 Dec 2018 → 31 Jul 2026
Jaypee Greens Kasa Isles, NoidaJaypee Infratech LimitedNoida291 mo31 Mar 2020 → 09 Oct 2027
Rhythm County (Phase 2)Futureworld Greenhomes Pvt. Ltd.Noida591 mo31 Dec 2019 → 31 Jul 2027
Rhythm County (Phase 1)Futureworld Greenhomes Pvt. Ltd.Greater Noida691 mo31 Dec 2018 → 31 Jul 2026
Jaypee Greens Kosmos A (Phase 2), NoidaJaypee Infratech LimitedNoida190 mo31 Mar 2019 → 29 Sep 2026
KVD WindparkKV Developers Private LimitedNoida289 mo07 Oct 2021 → 10 Mar 2029

How to read one project's full extension history

Open any delayed project's page and its completion-date section lays out every step: the originally declared date, then each extension in sequence with the revised date and the months it added, ending at the date currently on file. The same information sits in a dated table further down the page, extension by extension, so nothing about the timeline has to be inferred or taken on faith.

What a delayed listing does not tell you

A slip of a given size doesn't say why the date moved, whether the promoter is otherwise reliable, or how the current pace of construction compares to what's left on the clock. Read what an extension does and doesn't establish first, then weigh it against the promoter's wider record. Confirm the number on up-rera.in before treating anything here as final: this page mirrors that record, it isn't the record.

Reading a specific project?

Talk to an advisor who takes you through its filings, before any decision.